It was a really enjoyable visit today, as progress this week has been incredible.
This post has photo updates from each day this week to show the considerable progression.
Monday:
The the main external frames were positions and the subfloor fitted.
Tuesday:
The floor insulation and floor board fitting began and the internal partition walls were positioned.
Wednesday:
The rest of the floor was completed, and all the internal frame works were fitted and secured and the door openings were created.
Thursday:
The veranda was completed, and they began fixing the OSB cladding.
Friday:
The rest of the OSB was put up.
The pillars were trimmed and the south wall plate positioned and the glulam purlin was partially lifted into place.
As the building is being enclosed you really begin to get a feeling of the airy large interior, and the views that are framed by the chunky wooden frame are really looking nice.